화력발전소 원료 공급계획을 위한 휴리스틱 알고리즘
DC Field | Value | Language |
---|---|---|
dc.contributor.author | 김철연 | - |
dc.contributor.author | 문형근 | - |
dc.contributor.author | 최경현 | - |
dc.date.accessioned | 2022-07-16T20:08:06Z | - |
dc.date.available | 2022-07-16T20:08:06Z | - |
dc.date.created | 2021-05-13 | - |
dc.date.issued | 2011-06 | - |
dc.identifier.issn | 1225-0988 | - |
dc.identifier.uri | https://scholarworks.bwise.kr/hanyang/handle/2021.sw.hanyang/168188 | - |
dc.description.abstract | This paper deals with a coal supply planning problem for power plants. We propose a mathematical optimization model to make decisions for coal pile sections, movement of reclaimers, and operation time of conveyor belts. The objective of the proposed model is to minimize the total operation time of conveyor belts and total movement time of reclaimers. The algorithm firstly selects a pile section by considering both the location of reclaimers and the stock amount on that pile section. And then the shortest path from the selected pile section has to be put into the operation schedule and check whether the total operation time is satisfied. Then finally the new schedule is updated. To this end, we have tested the proposed algorithm comparing with the general standard optimization package for the simplified problem SCSPP. From the numerous test runs for comparing with the existing coal supply scheduling methods, We see that the proposed model may improve the coal supply operation by reducing significant coal supply costs. | - |
dc.language | 한국어 | - |
dc.language.iso | ko | - |
dc.publisher | 대한산업공학회 | - |
dc.title | 화력발전소 원료 공급계획을 위한 휴리스틱 알고리즘 | - |
dc.title.alternative | A Heuristic Algorithm for Power Plant Coal Supply Planning Problems | - |
dc.type | Article | - |
dc.contributor.affiliatedAuthor | 최경현 | - |
dc.identifier.doi | 10.7232/JKIIE.2011.37.2.132 | - |
dc.identifier.bibliographicCitation | 대한산업공학회지, v.37, no.2, pp.132 - 143 | - |
dc.relation.isPartOf | 대한산업공학회지 | - |
dc.citation.title | 대한산업공학회지 | - |
dc.citation.volume | 37 | - |
dc.citation.number | 2 | - |
dc.citation.startPage | 132 | - |
dc.citation.endPage | 143 | - |
dc.type.rims | ART | - |
dc.identifier.kciid | ART001554587 | - |
dc.description.journalClass | 2 | - |
dc.description.isOpenAccess | N | - |
dc.description.journalRegisteredClass | kci | - |
dc.subject.keywordAuthor | Power Plants | - |
dc.subject.keywordAuthor | the Coal Supply Planning | - |
dc.subject.keywordAuthor | Optimization | - |
dc.subject.keywordAuthor | the Operation Schedule | - |
dc.subject.keywordAuthor | Heuristic | - |
dc.identifier.url | http://koreascience.or.kr/article/JAKO201119342675996.page | - |
Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.
222, Wangsimni-ro, Seongdong-gu, Seoul, 04763, Korea+82-2-2220-1365
COPYRIGHT © 2021 HANYANG UNIVERSITY.
Certain data included herein are derived from the © Web of Science of Clarivate Analytics. All rights reserved.
You may not copy or re-distribute this material in whole or in part without the prior written consent of Clarivate Analytics.