수정 델파이 조사를 활용한 중·소규모 건설공사 생산성 저해 요인 분석 및 대응 방안 제시Analysis of Productivity Impeding Factors and Suggestion of Countermeasures in Small and Medium-Sized Construction Project through Modified Delphi Survey

Other Titles
Analysis of Productivity Impeding Factors and Suggestion of Countermeasures in Small and Medium-Sized Construction Project through Modified Delphi Survey
Authors
홍영록임정호장재호김주형이경태
Issue Date
Jan-2023
Publisher
대한건축학회
Keywords
중·소규모 건설공사; FGI 기법; 수정 델파이 조사; 생산성; Small and medium-sized construction project; Focus Group Interviews; Modified Delphi survey; Productivity
Citation
대한건축학회논문집, v.39, no.1, pp 321 - 330
Pages
10
Indexed
SCOPUS
KCI
Journal Title
대한건축학회논문집
Volume
39
Number
1
Start Page
321
End Page
330
URI
https://scholarworks.bwise.kr/hanyang/handle/2021.sw.hanyang/195728
DOI
10.5659/JAIK.2023.39.1.321
ISSN
2733-6239
2733-6247
Abstract
중소 규모 건설공사는 대다수의 중소기업이 운영하고 있으며, 이는 우리나라 건설공사의 절대 다수를 차지하고 있다. 하지만 중소규모 건설공사를 관리하면서 대규모 건설 프로젝트와 동일하게 생산성 향상방안을 구축하는 것뿐 아니라, 현장 관리자들의 생산성에 대한 인식이 부족하여 경제적 손실이나 안전문제가 다수 발생하고 있다. 따라서, 공사 진행 중 생산성 저해를 일으키는 주요 요인과 발생하는 원인을 규명, 생산성 향상을 위한 마련책을 제시하는 것이 필요하다. 그러므로 본 연구는 문헌고찰과 표적 집단 면접법을 통한 사전조사를 통해 중소규모 건설 프로젝트의 생산성 저해요인 분류체계 및 프레임워크를 수립하였고 2라운드로 구성된 수정 델파이 조사를 진행하였다. 그 결과, 작업자의 책임감 부족, 설계도서 미흡, 시공성을 무시한 설계도서, 과다한 설계도서 변경, 공사 계획 맞지 않는 작업자 투입, 잘못된 작업 계획, 작업 공종 간의 간섭, 방해, 공사 기간의 부족, 안전사고 발생이 중소 규모 건설공사의 생산성 주요 저해요인으로 선정하였다. 마지막으로 각 요인들의 발생 원인 및 개선방안 도출을 위해 전문가들과 인터뷰를 진행한 결과, 불성실한 현장 노동자들, 초기 단계부터 부족한 설계 및 공사 진행방식이 대표적인 생산성 저해 원인임을 파악하였으며, 작업자에 대한 명확한 교육, 중소규모 공사 특성에 맞춘 공사비 산정방식, 스마트 건설기술 도입을 통한 새로운 관리방식을 통해 중소규모 건설공사의 생산성을 향상시킬 수 있어야 한다.
Small and medium-sized construction projects account for the absolute majority of construction projects in Korea and contribute greatly to thenational economic development. However, there is a lack of awareness of productivity in small and medium-sized projects, resulting in anumber of economic losses or safety problems. Therefore, it is necessary to identify major factors and causes that hinder productivity duringconstruction and to suggest measures to improve productivity. This study established a classification system for factors impeding productivitythrough systematic literature review and Focus group interview as preliminary investigation. Through a two rounds of Modified Delphimethod, the lack of worker responsibility, irresponsible drawing plan that ignore site conditions and construction ability, excessive designchanges, incorrect work plan, interference between tasks due to urgent works, lack of safety issues were chosen as major factors impedingproductivity. As a result of conducting interviews with experts to derive the cause of the factors and improvement measures, it was foundthat insincere manpower and incorrect design and construction plan in the initial stage impeded productivity severe. Consequently, vocationaleducation for workers, introduction of modified cost calculation methods for small and medium-sized construction, and the active introductionof smart technology need to be conducted to improve productivity in small and medium-sized construction projects. This provides atheoretical basis for future research on the productivity of small and medium-sized construction projects and suggests solutions to the futurecrisis facing small and medium-sized construction companies.
Files in This Item
Go to Link
Appears in
Collections
서울 공과대학 > 서울 건축공학부 > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Related Researcher

Researcher Kim, Ju Hyung photo

Kim, Ju Hyung
COLLEGE OF ENGINEERING (SCHOOL OF ARCHITECTURAL ENGINEERING)
Read more

Altmetrics

Total Views & Downloads

BROWSE