연구로 안전 해체를 위한 스케쥴링 최적화
DC Field | Value | Language |
---|---|---|
dc.contributor.author | 김태성 | - |
dc.contributor.author | 이종환 | - |
dc.contributor.author | 장성호 | - |
dc.contributor.author | 김상호 | - |
dc.contributor.author | 박희성 | - |
dc.date.available | 2020-04-24T14:25:41Z | - |
dc.date.created | 2020-03-31 | - |
dc.date.issued | 2006 | - |
dc.identifier.issn | 1229-6783 | - |
dc.identifier.uri | https://scholarworks.bwise.kr/kumoh/handle/2020.sw.kumoh/3335 | - |
dc.description.abstract | Scheduling of dismantling old research reactor need to consider time, cost and safety for the worker. The biggest issue when dismantling facility for research reactor is safety for the worker and cost. Large portion of a budget is spending for the labor cost. To save labor cost for the worker, reducing a lead time is inevitable. Several algorithms applied to reduce read time, and safety considered as the most important factor for this project. This research presents three different dismantling scheduling scenarios. Best scenario shows the specific scheduling for worker and machine, so that it could save time and cost. | - |
dc.publisher | 대한안전경영과학회 | - |
dc.title | 연구로 안전 해체를 위한 스케쥴링 최적화 | - |
dc.title.alternative | Scheduling Optimization for Safety Decommissioning of Research Reactor | - |
dc.type | Article | - |
dc.contributor.affiliatedAuthor | 김태성 | - |
dc.contributor.affiliatedAuthor | 이종환 | - |
dc.contributor.affiliatedAuthor | 장성호 | - |
dc.contributor.affiliatedAuthor | 김상호 | - |
dc.identifier.bibliographicCitation | 대한안전경영과학회지, v.8, no.4, pp.67 - 75 | - |
dc.citation.title | 대한안전경영과학회지 | - |
dc.citation.volume | 8 | - |
dc.citation.number | 4 | - |
dc.citation.startPage | 67 | - |
dc.citation.endPage | 75 | - |
dc.type.rims | ART | - |
dc.identifier.kciid | ART001168736 | - |
dc.description.journalClass | 2 | - |
dc.subject.keywordAuthor | Research reactor | - |
dc.subject.keywordAuthor | Scheduling optimization | - |
dc.subject.keywordAuthor | Safety | - |
dc.subject.keywordAuthor | Dismantling procedure | - |
dc.subject.keywordAuthor | Research reactor | - |
dc.subject.keywordAuthor | Scheduling optimization | - |
dc.subject.keywordAuthor | Safety | - |
dc.subject.keywordAuthor | Dismantling procedure | - |
Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.
350-27, Gumi-daero, Gumi-si, Gyeongsangbuk-do, Republic of Korea (39253)054-478-7170
COPYRIGHT 2020 Kumoh University All Rights Reserved.
Certain data included herein are derived from the © Web of Science of Clarivate Analytics. All rights reserved.
You may not copy or re-distribute this material in whole or in part without the prior written consent of Clarivate Analytics.