Detailed Information

Cited 0 time in webofscience Cited 0 time in scopus
Metadata Downloads

설계변경 재고 소진 최적화: E社 펌프카 아우트리거 공정 중심으로Optimizing the Exhaustion of Inventory for Design Changes: Focusing on Concrete Pump Truck Outrigger Process

Other Titles
Optimizing the Exhaustion of Inventory for Design Changes: Focusing on Concrete Pump Truck Outrigger Process
Authors
박찬웅
Issue Date
Dec-2022
Publisher
한국산업경영시스템학회
Keywords
Exhaustion of Inventory; Design Changes; Concrete Pump Truck
Citation
한국산업경영시스템학회지, v.45, no.4, pp.174 - 179
Journal Title
한국산업경영시스템학회지
Volume
45
Number
4
Start Page
174
End Page
179
URI
https://scholarworks.bwise.kr/gachon/handle/2020.sw.gachon/86384
ISSN
2005-0461
Abstract
Companies are making design changes by improving product quality and function to succeed while meeting customer requirements continuously. Design changes are changing the product BOM's amount, item, specification, and shape while causing a change in the product's structure. At this time, the problem of inventory exhaustion of parts before design change is a big topic. If the inventory exhaustion fails, the pieces before the design change become unused and are discarded, resulting in a decrease in asset value, and the quality cost of the design change affects the company's profits. Therefore, it is necessary to decide to minimize quality costs while minimizing waste inventory costs at the time of application of design changes. According to the analysis, priorities should be prioritized according to urgency because the quantity of items before the design change affects the applied lead time.
Files in This Item
There are no files associated with this item.
Appears in
Collections
공과대학 > 산업경영공학과 > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Related Researcher

Researcher Park, Chan Woong photo

Park, Chan Woong
Engineering (Department of Industrial Engineering)
Read more

Altmetrics

Total Views & Downloads

BROWSE