시공단계에 참여하는 전문건설업체를 위한 시공 BIM 수행계획 구축 - 철근콘크리트 업체를 중심으로A Study about BIM Execution Plan for Specialty Contractors at Construction Phase - focused on Specialty Contractors in Reinforced Concrete Works -

Other Titles
A Study about BIM Execution Plan for Specialty Contractors at Construction Phase - focused on Specialty Contractors in Reinforced Concrete Works -
Authors
이주성함남혁김재준
Issue Date
Sep-2015
Publisher
한국BIM학회
Keywords
BIM(Building Information Modeling); Construction BIM; BIM PxP(Project Execution Plan); Reinforced Concrete; 빌딩정보모델링; 시공 BIM; BIM 수행계획서; 철근 콘크리트
Citation
한국BIM학회 논문집, v.5, no.3, pp.19 - 32
Indexed
OTHER
Journal Title
한국BIM학회 논문집
Volume
5
Number
3
Start Page
19
End Page
32
URI
https://scholarworks.bwise.kr/hanyang/handle/2021.sw.hanyang/156335
DOI
10.13161/kibim.2015.5.3.019
ISSN
2288-1697
Abstract
For decades, the productivity issue has been a primary concern for the all stake-holders who participate in domestic construction industry. Especially, between a whole life cycle of building, the construction phase's productivity problem makes or break the entire project. In this respect, the general construction company, who accept the order and construct the building(so called General Contractor), should consider various strategies, such as schedule management, cost management, quality management, inner-crew management, etc., for the productivity improvement., and almost of these management methods have been studied for a long time. But, the researches and studies about the specialty contractor, who construct the building directly in construction site were not sufficiently complete yet. This research begins as an idea which tries to apply the BIM(Building Information Modeling) into the tasks of Specialty contractors for their productivity improvement. And for the effective application of construction BIM to specialty contractors, establish of the BIM project execution plan for them, not the fragmentary adoption of BIM. Therefore, in this paper, we develop the BIM project execution plan for the reinforced concrete companies who conduct the framework construction which located on CP(Critical Path) Especially, we model the "Construction BIM Use List for the RC Work", "BIM Application Master Process" and "BIM Application Detailed Process", and general contractor who use these BIM uses list and process models can manage various specialty contractors about schedule, cost, earned value, quality, safety and environment management systematically.
Files in This Item
Go to Link
Appears in
Collections
서울 공과대학 > 서울 건축공학부 > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Related Researcher

Researcher Kim, Jae Jun photo

Kim, Jae Jun
COLLEGE OF ENGINEERING (SCHOOL OF ARCHITECTURAL ENGINEERING)
Read more

Altmetrics

Total Views & Downloads

BROWSE