Study on the major delay factors in finishing works before completion of construction
- Authors
- Kim, Min Seok; Yoo, Seung Kyu; Kim, Ju Hyung; Kim, Jae Jun
- Issue Date
- Jun-2011
- Publisher
- International Association for Automation and Robotics in Construction I.A.A.R.C)
- Keywords
- Delay of construction period; Finishing work; Process management
- Citation
- Proceedings of the 28th International Symposium on Automation and Robotics in Construction, ISARC 2011, pp.1507 - 1510
- Indexed
- SCOPUS
- Journal Title
- Proceedings of the 28th International Symposium on Automation and Robotics in Construction, ISARC 2011
- Start Page
- 1507
- End Page
- 1510
- URI
- https://scholarworks.bwise.kr/hanyang/handle/2021.sw.hanyang/168274
- DOI
- 10.22260/isarc2011/0290
- ISSN
- 2413-5844
- Abstract
- There are many variations and risks in construction work and the risk is getting increased in accordance of big scale, variation and complexity for the construction work. If the process management is not planned thoroughly, it affects the construction period. The delay of construction period causes the increase of project budget and low productivity and it is the cause of poor construction for recovering the long-term suspension of construction in construction work. There are various problems such as low quality, negligent accidents, etc. Especially, the delay of finishing work can be fatal before the completion of construction. It is study on analysis of the influence factor for delay of construction period and how to apply in real work site in finishing work. It is regarded that this study will lead to thorough process movement in work site and critical data.
- Files in This Item
-
Go to Link
- Appears in
Collections - 서울 공과대학 > 서울 건축공학부 > 1. Journal Articles