선박건조공정의 미세 통합 일정 관리 체계 구축에 관한 연구A Study on the Construction of Detail Integrated Scheduling Systemof Ship Building Process

Other Titles
A Study on the Construction of Detail Integrated Scheduling Systemof Ship Building Process
Authors
김용섭이대형
Issue Date
2007
Publisher
대한조선학회
Keywords
IHOP; Scheduling; Dock process; 미세 통합 일정 관리체계 구축; 일정계획; DOCK공정
Citation
대한조선학회 논문집, v.44, no.1, pp.48 - 54
Journal Title
대한조선학회 논문집
Volume
44
Number
1
Start Page
48
End Page
54
URI
https://scholarworks.bwise.kr/hongik/handle/2020.sw.hongik/24113
ISSN
1225-1143
Abstract
Higher productivity and less cost during the manufacturing process of ships are required to maintain international competitiveness of modern shipbuilding industries. The integrated hull/ outfitting/ painting scheduling(IHOP) process is a final point, where logistics are finally being integrated and upcoming schedules are made. Therefore, more profits are expected from IHOP by effective management. In this thesis, IHOP is proposed in order to solve how to choose block erection date with IHOP scheduling logic. The result of IHOP scheduling is highly advised to utilize fabrication, outfitting shops. A standardized operation and load of resource will eventually be applied in long-term time span point of view for this will make it easy to enable capacity planning and workforce planning. It is also expected to eliminate inefficiency in overtime work and efficiently utilize manpower in short-term.
Files in This Item
There are no files associated with this item.
Appears in
Collections
College of Science and Technology > Department of Naval Architecture and Ocean Engineering > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Altmetrics

Total Views & Downloads

BROWSE