단위작업 물량 달성율과 투입 노무량을 이용한 진도율 산정방법에 관한 연구- 공동주택공사의 골조공사를 중심으로 -A Study on the Progress Measurement Method using Percent Complete of Work and Labor Productivity- Focusing on Structural Works of Apartment Construction -

Other Titles
A Study on the Progress Measurement Method using Percent Complete of Work and Labor Productivity- Focusing on Structural Works of Apartment Construction -
Authors
최현하이준복
Issue Date
2005
Publisher
한국건설관리학회
Keywords
apartment housing; progress management; progress rate; activity; percent complete of work; manhours; weighted value; apartment housing; progress management; progress rate; activity; percent complete of work; manhours; weighted value; 공동주택; 공정관리; 진도율; 단위작업; 물량달성도; 투입노무량; 가중치
Citation
한국건설관리학회 논문집, v.6, no.1, pp.212 - 219
Journal Title
한국건설관리학회 논문집
Volume
6
Number
1
Start Page
212
End Page
219
URI
https://scholarworks.bwise.kr/hongik/handle/2020.sw.hongik/25610
ISSN
2005-6095
Abstract
건설공사에서 공정관리는 중요하다. 특히 공동주택의 경우 입주일이라는 절대공기의 준수가 매우 중요하다. 이와 같은 공정관리를 위해 공동주택공사에서는 공종별 진도관리가 필요하며, 이는 진도율 산정을 통하여 일정계산 및 기성 산정의 척도로서 사용되고 있다. 현재 국내의 공동주택 건설현장에서 사용되고 있는 대부분의 진도율 산정방식은 경험과 개략적인 수치에 의한 판단에 의존하는 경우가 많아 공정의 계획과 공정의 지연시 합리적 만회 대책의 수립이 어려운 등 한계를 보이고 있다. 이와 같은 문제를 해결하기 위하여 본 연구에서는 단위작업에서의 물량 달성율과 투입 노무량을 이용한 진도율 산정방식을 제시하고 있다. 즉, 단위작업 진도율은 단위작업에서 수집된 투입 노무량을 층단위의 전체 투입노무량 중의 가중치로 환산하고 이를 물량달성도(%)와 곱하여 산출된다. 같은 방법으로 본 연구에서 제시하고 있는 작업분류체계의 상위단계인 층 진도율, 동 진도율을 산출하게 된다. 공동주택공사의 골조공사를 대상으로 단위작업, 층, 동 진도율 산정방법을 예시로서 제시하고 있다. 이와 같은 진도율은 향후 단위작업의 노무생산성과 달성물량에 대한 실적데이터의 축적이 이루어질 경우 보다 합리적이고 과학적인 공정관리의 근간이 될 것으로 기대된다.
Files in This Item
There are no files associated with this item.
Appears in
Collections
ETC > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Altmetrics

Total Views & Downloads

BROWSE