해외 플랜트 건설사업 위험요인을 통한 비용 변동범위 분석A Study on the Costs Variation Range through the Risk Factors for Overseas Plant Projects

Authors
강현욱민병준김용수
Issue Date
2010
Publisher
대한건축학회
Keywords
Overseas Plant Construction; EPC Phase; Risk Factor; Costs Variation Range; Monte-Carlo Simulation; 해외 플랜트; EPC단계; 위험요인; 비용 변동율; 비용 변동범위; 몬테카를로 시뮬레이션
Citation
대한건축학회논문집 구조계, v.26, no.07, pp 139 - 146
Pages
8
Journal Title
대한건축학회논문집 구조계
Volume
26
Number
07
Start Page
139
End Page
146
URI
https://scholarworks.bwise.kr/cau/handle/2019.sw.cau/34250
ISSN
1226-9107
Abstract
The purpose of this study is to analysis costs variation range through the risk factors for overseas plant projects. For this study, risk factors data from related literature review, research organization and construction company was researched and classified under each E(Engineering)P(Procurment)C(Construction) phases. The adapted research method through the questionnaire survey by plant experts was conducted for analysis of probability index and costs variation rate. Based on costs variation rate for each risk factors, the adapted research method includes application of average cost for three cases. And through Monte-Carlo Simulation, analysis of cost variation range was conducted. The results of this study are as follows: 1) The analysis of risk factors through the costs variation rate for EPC phase is Design costs variation rate -14.63%, +25.56%, Procurement costs variation rate -21.39%, +37.63%, Construction costs variation rate -31.47%, +47.07%. the analysis of costs variation range for application total average costs of three cases is to average costs 163,457 USD, maximum costs 213,710 USD, minimum costs 123,249 USD. 2) The analysis of relatively high risk factors probability index is to Design costs variation rate -7.8% +16.11%,Procurement costs variation rate -6.76%, +15.73%, Construction costs variation rate -14.72%, +25.64%. The results of costs variation range for the total average costs application of three cases is average costs 160,599 USD, maximum costs 184,635 USD,minimum costs 141,929 USD
Files in This Item
There are no files associated with this item.
Appears in
Collections
College of Engineering > School of Architecture and Building Science > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Altmetrics

Total Views & Downloads

BROWSE