Scheduling algorithms to minimize the number of tardy jobs in two-stage hybrid flow shops
- Authors
- Choi, Hyun-Seon; Lee, Dong-Ho
- Issue Date
- Feb-2009
- Publisher
- Pergamon Press Ltd.
- Keywords
- Scheduling; Two-stage hybrid flow shop; Number of tardy jobs; Branch and bound; Heuristics
- Citation
- Computers and Industrial Engineering, v.56, no.1, pp 113 - 120
- Pages
- 8
- Indexed
- SCIE
SCOPUS
- Journal Title
- Computers and Industrial Engineering
- Volume
- 56
- Number
- 1
- Start Page
- 113
- End Page
- 120
- URI
- https://scholarworks.bwise.kr/hanyang/handle/2021.sw.hanyang/177344
- DOI
- 10.1016/j.cie.2008.04.005
- ISSN
- 0360-8352
1879-0550
- Abstract
- This paper considers a two-stage hybrid flow shop scheduling problem for the objective of minimizing the number of tardy jobs. Each job is processed through the two production stages in series, each of which has multiple identical parallel machines. The problem is to determine the allocation of jobs to the parallel machines as well as the sequence of the jobs assigned to each machine. To solve the problem, a branch and bound algorithm, which incorporates the methods to obtain the lower and upper bounds as well as the dominance properties to reduce the search space, is suggested that gives the optimal solutions. In addition, two-phase heuristic algorithms are suggested to obtain good solutions for large-size problems within a reasonable amount of computation time. To show the performances of the optimal and heuristic algorithms suggested in this paper, computational experiments are done on a number of randomly generated test problems, and the test results are reported.