연구로 안전 해체를 위한 스케쥴링 최적화Scheduling Optimization for Safety Decommissioning of Research Reactor

Other Titles
Scheduling Optimization for Safety Decommissioning of Research Reactor
Authors
김태성이종환장성호김상호박희성
Issue Date
2006
Publisher
대한안전경영과학회
Keywords
Research reactor; Scheduling optimization; Safety; Dismantling procedure; Research reactor; Scheduling optimization; Safety; Dismantling procedure
Citation
대한안전경영과학회지, v.8, no.4, pp.67 - 75
Journal Title
대한안전경영과학회지
Volume
8
Number
4
Start Page
67
End Page
75
URI
https://scholarworks.bwise.kr/kumoh/handle/2020.sw.kumoh/3335
ISSN
1229-6783
Abstract
Scheduling of dismantling old research reactor need to consider time, cost and safety for the worker. The biggest issue when dismantling facility for research reactor is safety for the worker and cost. Large portion of a budget is spending for the labor cost. To save labor cost for the worker, reducing a lead time is inevitable. Several algorithms applied to reduce read time, and safety considered as the most important factor for this project. This research presents three different dismantling scheduling scenarios. Best scenario shows the specific scheduling for worker and machine, so that it could save time and cost.
Files in This Item
There are no files associated with this item.
Appears in
Collections
School of Industrial Engineering > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Related Researcher

Researcher KIM, TAE SUNG photo

KIM, TAE SUNG
College of Engineering (Department of Industrial Engineering)
Read more

Altmetrics

Total Views & Downloads

BROWSE