해외 가스 플랜트 건설사업의 위험요인을 고려한 비용분석 모델에 관한 연구A Study on the Cost Analysis Model based on Risk Factors of the Overseas Gas Plant Construction Industry

Authors
박문선김용수
Issue Date
2015
Publisher
대한건축학회
Keywords
Gas Plant; Cost Analysis; Fuzzy Method; Monte Carlo Method; Risk Analysis; 가스 플랜트; 비용 분석; 퍼지 기법; 몬테카를로 시뮬레이션 기법; 위험 분석
Citation
대한건축학회논문집 구조계, v.31, no.3, pp 53 - 62
Pages
10
Journal Title
대한건축학회논문집 구조계
Volume
31
Number
3
Start Page
53
End Page
62
URI
https://scholarworks.bwise.kr/cau/handle/2019.sw.cau/11143
DOI
10.5659/JAIK_SC.2015.31.3.53
ISSN
1226-9107
Abstract
The purpose of this study is to suggest a cost analysis model based on risk factors that can be used in the gas plant construction industry. The research method of this study is to examine and analyze construction stage details of five construction companies with experience of gas plant construction, and construction stage risk factors of domestic construction industry, domestic research institutions, and foreign institutions. In addition, a cost analysis model is suggested by using Fuzzy analysis and Monte Carlo simulation. The results of this study are as follows: First, construction stage details of five construction companies with experience of gas plant construction were examined and analyzed, and through this, a cost breakdown structure (1 Level∼4 Level) is suggested. And construction stage risk factors of domestic construction industry, domestic research institutions, and foreign institutions were examined and analyzed, and through this, 16 risk factors were drawn from domestic construction industry, 18 from domestic research institutions, and 16 from foreign institutions, and finally 28 risk factors were drawn after rearrangement. Second, triangular distribution is applied based on the construction stage cost breakdown structure and the risk factors, and here, with Fuzzy analysis, minimum and maximum values of the risk factors were analyzed and drawn through interviews with experts, and with Monte Carlo simulation, the risk factors were applied to the cost breakdown structure through interviews with experts, and the result values drawn through Fuzzy analysis were also applied to the cost breakdown structure. Additionally, as a result of verifying the cases with an analysis tool, @Risk, through the method above, it could be found that among the cost items reflecting the risk factors, construction cost, outsourcing cost, construction equipment cost, site management cost, water, light, and heat expenses, and safety management cost show cost variability through the bidding feasibility analysis model of this study.
The purpose of this study is to suggest a cost analysis model based on risk factors that can be used in the gas plant construction industry. The research method of this study is to examine and analyze construction stage details of five construction companies with experience of gas plant construction, and construction stage risk factors of domestic construction industry, domestic research institutions, and foreign institutions. In addition, a cost analysis model is suggested by using Fuzzy analysis and Monte Carlo simulation. The results of this study are as follows: First, construction stage details of five construction companies with experience of gas plant construction were examined and analyzed, and through this, a cost breakdown structure (1 Level∼4 Level) is suggested. And construction stage risk factors of domestic construction industry, domestic research institutions, and foreign institutions were examined and analyzed, and through this, 16 risk factors were drawn from domestic construction industry, 18 from domestic research institutions, and 16 from foreign institutions, and finally 28 risk factors were drawn after rearrangement. Second, triangular distribution is applied based on the construction stage cost breakdown structure and the risk factors, and here, with Fuzzy analysis, minimum and maximum values of the risk factors were analyzed and drawn through interviews with experts, and with Monte Carlo simulation, the risk factors were applied to the cost breakdown structure through interviews with experts, and the result values drawn through Fuzzy analysis were also applied to the cost breakdown structure. Additionally, as a result of verifying the cases with an analysis tool, @Risk, through the method above, it could be found that among the cost items reflecting the risk factors, construction cost, outsourcing cost, construction equipment cost, site management cost, water, light, and heat expenses, and safety management cost show cost variability through the bidding feasibility analysis model of this study.
Files in This Item
There are no files associated with this item.
Appears in
Collections
College of Engineering > School of Architecture and Building Science > 1. Journal Articles

qrcode

Items in ScholarWorks are protected by copyright, with all rights reserved, unless otherwise indicated.

Altmetrics

Total Views & Downloads

BROWSE